Contract awarded for Cut Throat Lane switching station move
East West Rail Company Limited intends to award a £22.1m package to relocate a 132kV switching station north of Bedford.
- Package value
- £22,076,599.33
- Client
- East West Rail Company Limited
- Supplier
- UK Power Networks Operations Ltd
- Event date
- 11 November 2026
Where it is
What happened
East West Rail Company Limited intends to award a £22,076,599.33 package directly to UK Power Networks Operations Ltd for the Relocation of 132kV UKPN Cut Throat Lane Switching Station. The notice was published on 11 November 2026, and the event is dated 11 November 2026.
The existing switching station is at Fairfield Park / Cut Throat Lane, north of Bedford. It sits within the footprint of the proposed six-track railway corridor, so it must be relocated to enable construction of the railway.
The package covers the design, decommissioning, relocation, installation, testing and commissioning of a replacement 132kV switching station. It also includes associated electrical, civil and enabling works needed to maintain network resilience and continuity of supply while services transfer from the existing installation to the replacement facility.
Who builds it
The client is East West Rail Company Limited, identified in the notice as the Authority delivering the East West Rail programme. That programme is described as a nationally significant infrastructure project providing new and upgraded rail connections between Oxford, Milton Keynes, Bedford and Cambridge.
The intended supplier is UK Power Networks Operations Ltd. The notice says the company owns and operates the affected 132kV electricity distribution assets and is the licensed Distribution Network Operator for the network concerned.
The procurement notice says the requirement comprises non-contestable electricity network works that may only be undertaken by the licensed Distribution Network Operator under the statutory framework established by the Electricity Act 1989, as amended. It says UK Power Networks Operations Ltd is the only organisation with the legal authority and technical responsibility to undertake the required works.
East West Rail Company Limited therefore intends to make a direct award. The notice says the Authority considers the conditions for a direct award under Schedule 5, Paragraph 5 (a) and (b) of the Procurement Act 2023 are satisfied because the works can only be supplied by a particular supplier due to the absence of competition arising from exclusive rights.
What the gate will ask for
The stated work packages are the design, decommissioning, relocation, installation, testing and commissioning of the replacement switching station, together with electrical, civil and enabling works. Have a RAMS ready for the relevant work packages and make sure the people carrying out the work have the required CSCS cards and site inductions; Build a RAMS can help structure the method statement.
Why it is in the news
The package is significant because it is required to clear an existing 132kV electricity installation from the proposed railway works. The railway infrastructure is planned as part of a six-track corridor north of Bedford, and the switching station currently lies within that footprint.
The value published for the award is £22,076,599.33. This is a defined package for the replacement switching station and its associated works, rather than a value for the wider East West Rail programme.
The work is also notable because the notice describes the electrical network activities as non-contestable. UK Power Networks Operations Ltd is named as both the owner and operator of the affected assets and the licensed Distribution Network Operator, supporting the stated direct-award route.
The package must allow services to transfer from the existing installation to the replacement facility while maintaining network resilience and continuity of supply. That places the electrical, civil and enabling elements alongside the railway interface as the central delivery issue.
Official sources
- Find a Tender — Relocation of 132kV UKPN Cut Throat Lane Switching Station
Follow Relocation of 132kV UKPN Cut Throat Lane Switching Station
One email when this project changes: contractor, start date, delay, cost. Nothing else.
Or every new site within 25 miles of your postcode, every Monday.
We sent a link to . Click it and you will hear when Relocation of 132kV UKPN Cut Throat Lane Switching Station changes.
Know something about this project?Tell us privately. It is not published.
We will check it against official sources. If it is confirmed, this page and its followers are updated.