Introduction This document describes the legal framework and the role HSE has in ensuring safety at Liquefied Natural Gas (LNG) terminals in the UK.
HSE's primary role and regulatory responsibilities for ensuring safety are during the design, construction, and operation of LNG terminals and ensuring appropriate emergency plans are developed. This document also describes the legal framework and HSE's advisory role in the land use planning system. It also identifies the interfaces between HSE and other regulatory bodies who also have responsibilities associated with LNG terminals.
Quoted from HSE. Open the original on hse.gov.uk
Check your RAMS against this document
Related guidance
- HSE's role in gas supply emergencies
- Salt cavity natural gas storage - Consent and operational issues
- Gas supply legislation, guidance and submitting gas transporter safety cases
- The application of the Control of Major Accident Hazards Regulations 2015 (COMAH) and the Pipelines Safety Regulations 1996 (PSR) to the storage of natural gas at depleted reservoir and salt cavity sites
Tell me when HSE changes this
Tell me when HSE changes LNG terminals - Consent and operational issues. A line in the Monday email when HSE withdraws, replaces, moves or updates this document, and no email when it does not.
Contains public sector information published by the Health and Safety Executive and licensed under the Open Government Licence v3.0. KASQ is not affiliated with HSE.